TA2025-Monthly-Report-for-September-2025

Page 1


STATUS REPORT

TA 2026

SEPTEMBER 2025

195

DAYS TO TA 2026

ACTIVITY STATUS

Completed Activities:

Conducted meeting with IT TEAM

Conducted Meeting with Environment Section

Job list discussion is in progress for Methanol, Urea & Utilities Plants

Issuance of Turnaround Area Leaders List (Rev 05)

Issuance of Revised TA 2026 Roadmap.

Issuance of Organization chart (Area Leader level)

Issuance of Revised TA 2026 Master Schedule

Ongoing Activities:

Blocking of Stock Materials is in progress 92% completed

Detailed assessment for Critical/Major Jobs is in progress

Delivery of Capex Items are in progress

Technical evaluation & issuance of final recommendation memos for packages and Vendors are in progress

Material reservation for PM orders and CM orders is in progress: 98% and 91% completed respectively

Turnaround CM order assessment is in progress: 94% completed

TA Job list Review Meetings are in progress

Issuance of seconded manpower list

Issuance of Organization Charts (Technicians Level)

ACTIVITY STATUS

ROADMAP S-CURVE

Planned

Completed

Slippage

CM MATERIAL STATUS

Pending CM Material Reservation (No. of WOs)

PM MATERIAL STATUS

Pending PM Material Reservations (No. of WOs)

PR STATUS

REFURBISHMENT STATUS

Issued PO Status:

1. MG-6401 Exciter - DM+ (Expected to be delivered by end of October 2025)

TA AUDIT REPORT

Total of 9 Audits Conducted till August 2025 on turnaround planning department by TAT (Turnaround Audit team)

CAPEX PROJECTS TIMELINE

HIMA ESD System* PO Incl FSE (Material Received)

42 Fans for Air Cooler ** PO Incl FSE (Material Received)

LV-08009** Routine (Material Received)

33kV SWBD 61MS5-1** PO Includes FSE (Material Received)

Methanol PG Cooler E-1201** PR#7236 (AC) (Material Received)

December

January

April

Electronic Governor MT-0701 & MT-1401* PO Includes FSE (Material Received)

PSV-5253****, In-House Installation

HV-82009 ** Inhouse Installation

Trip Solenoid for Synth & Mug Turbines**** PR Includes FSE

E-8601 E-8602A/B/C

E-8604*, E-0704*, Inhouse Installation

Honeywell DCS* PO Includes FSE

MCR UPS

D-1501** Inhouse Installation, E-0001B**PR#7216 (AC) (Material Received)

Ammonia PG Cooler

E-0301** PR#7241 (AC)

Urea 2200 MTPD - MOV82003**** In-House Installation

HSV-52236 & HSV52336, Inhouse Installation

Urea ESD**** ENG PR Includes FSE

Super Cup Trays R8201** PR#7244 (TE)

MD-6102 PLC* PR Includes FSE

B-5203 ESD ****

LV-82011, HV-82005, HV-82008 ** Inhouse Installation

Urea Stripper

E-0003** PR#7216 (AC)

E-8201*** PR#7244 (AO) PV-52201/351 & PV-52401/402* In-House Installation

HP Carbamate

Seperator D-8201*** PR#7244(TE)

Passivation Air Compressor** PO Includes FSE

CONFIRMED MAJOR JOBS

Ammonia Plant

CONFIRMED MAJOR JOBS

Methanol Plant

Replacement of Process Gas Cooler (E-1201) at Methanol Plant

B-1201 Replacement of MTH reformer walls : 2 side walls (B-1201) [Recommended Option]

CONFIRMED MAJOR JOBS

Urea Plant

Utilites Plant