STATUS REPORT
TA 2026
SEPTEMBER 2025
195
DAYS TO TA 2026


ACTIVITY STATUS
Completed Activities:
Conducted meeting with IT TEAM
Conducted Meeting with Environment Section
Job list discussion is in progress for Methanol, Urea & Utilities Plants
Issuance of Turnaround Area Leaders List (Rev 05)
Issuance of Revised TA 2026 Roadmap.
Issuance of Organization chart (Area Leader level)
Issuance of Revised TA 2026 Master Schedule
Ongoing Activities:
Blocking of Stock Materials is in progress 92% completed
Detailed assessment for Critical/Major Jobs is in progress
Delivery of Capex Items are in progress
Technical evaluation & issuance of final recommendation memos for packages and Vendors are in progress
Material reservation for PM orders and CM orders is in progress: 98% and 91% completed respectively
Turnaround CM order assessment is in progress: 94% completed
TA Job list Review Meetings are in progress
Issuance of seconded manpower list
Issuance of Organization Charts (Technicians Level)

ACTIVITY STATUS

ROADMAP S-CURVE
Planned
Completed
Slippage
CM MATERIAL STATUS
Pending CM Material Reservation (No. of WOs)
PM MATERIAL STATUS
Pending PM Material Reservations (No. of WOs)
PR STATUS
REFURBISHMENT STATUS
Issued PO Status:
1. MG-6401 Exciter - DM+ (Expected to be delivered by end of October 2025)
TA AUDIT REPORT
Total of 9 Audits Conducted till August 2025 on turnaround planning department by TAT (Turnaround Audit team)
CAPEX PROJECTS TIMELINE
HIMA ESD System* PO Incl FSE (Material Received)
42 Fans for Air Cooler ** PO Incl FSE (Material Received)
LV-08009** Routine (Material Received)
33kV SWBD 61MS5-1** PO Includes FSE (Material Received)
Methanol PG Cooler E-1201** PR#7236 (AC) (Material Received)
December
January
April
Electronic Governor MT-0701 & MT-1401* PO Includes FSE (Material Received)
PSV-5253****, In-House Installation
HV-82009 ** Inhouse Installation
Trip Solenoid for Synth & Mug Turbines**** PR Includes FSE
E-8601 E-8602A/B/C
E-8604*, E-0704*, Inhouse Installation
Honeywell DCS* PO Includes FSE
MCR UPS
D-1501** Inhouse Installation, E-0001B**PR#7216 (AC) (Material Received)
Ammonia PG Cooler
E-0301** PR#7241 (AC)
Urea 2200 MTPD - MOV82003**** In-House Installation
HSV-52236 & HSV52336, Inhouse Installation
Urea ESD**** ENG PR Includes FSE
Super Cup Trays R8201** PR#7244 (TE)
MD-6102 PLC* PR Includes FSE
B-5203 ESD ****
LV-82011, HV-82005, HV-82008 ** Inhouse Installation
Urea Stripper
E-0003** PR#7216 (AC)
E-8201*** PR#7244 (AO) PV-52201/351 & PV-52401/402* In-House Installation
HP Carbamate
Seperator D-8201*** PR#7244(TE)
Passivation Air Compressor** PO Includes FSE
CONFIRMED MAJOR JOBS
Ammonia Plant
CONFIRMED MAJOR JOBS
Methanol Plant
Replacement of Process Gas Cooler (E-1201) at Methanol Plant
B-1201 Replacement of MTH reformer walls : 2 side walls (B-1201) [Recommended Option]
CONFIRMED MAJOR JOBS
Urea Plant
Utilites Plant